Tuesday, April 15, 2008

North Bennet Street School Comes for a Visit


On Thursday, April 10, architect Don Tellalian (pictured on the right), AIA of Tellalian Associates Architects & Planners, LLC met with the Preservation Carpentry class from North Bennet Street School. Taught by Robert Adam, the class was on-site to observe preservation carpentry first-hand as Rich Muckle and a crew from M&A Architectural Preservation, Inc. were working on the siding of the Old State House tower.

Wednesday, April 9, 2008

Exploring the Effects of Time and Weather: The Balustrades




This week our team has been up on the scaffolding exploring the damage that has been caused by time and weather. The goal with our preservation project is to save as much historic material as possible, but replace when necessary. The top and bottom rails on the tower balustrades are badly deteriorated and in need of work. The balusters themselves look to be in good condition and will be saved, but the rails will be replaced.

Friday, April 4, 2008

First Look





It has been a busy week here at the Old State House. Marr scaffolding was here finishing the stairs and safety rails so that the work crew will have access to the tower to begin the project next week.


Yesterday was the first up-close look that many of us had of the tower. Our excellent team, pictured above, of Don Tellalian, Judy Selwyn, Rich Muckle, and David Storeygard, examined the deterioration of the wood on the tower. This was also the first time in about 15 years that the weathervane on the dome has been seen up-close.


Stay tuned for more images and updates as the work gets underway next week.

Monday, March 31, 2008

More Photos from Sunday







Yesterday proved to be a long and exciting day as everyone worked from 6am until 10pm, but the hardest parts of laying out the scaffolding are now done.



These photos show the large beams (as seen in the photos from yesterday) being set in place by the crew from Marr Scaffolding, the beams being secured with welds, and work platforms being constructed.

Sunday, March 30, 2008

Crane Day








Sunday was crane day for the Tower Restoration Project at the Old State House. Beginning the day at 6am, our great team from Lee Kennedy, Marr Scaffolding and Crane, and T. G. Gallagher Mechanical Engineers have replaced the chiller, or cooling unit, for the Old State House HVAC system, placed 4 beams (weighing 6,000 pounds each) on the scaffolding, and started construction on the work platforms around the tower itself. There will be more pictures on the way from this exciting day!

Friday, March 28, 2008

Pre-crane Work Stopped By Rain


Last night's scheduled scaffold assembly was postponed due to rain. The work is back on for tonight and the north side of the building will be finished before Sunday.
Sunday morning will be a busy day at the Old State House: the crane will be onsite to lift the large support beams for the upper scaffolding.

Tuesday, March 25, 2008

Scaffolding Begins


This morning the staff at the Old State House came into work and saw partial scaffolding erected on the south side of the building. The first stage of scaffolding will reach the peak of the roof and will be finished prior to the coming weekend. The project began last night and more scaffolding will be added each night this week.