Friday, March 28, 2008

Pre-crane Work Stopped By Rain


Last night's scheduled scaffold assembly was postponed due to rain. The work is back on for tonight and the north side of the building will be finished before Sunday.
Sunday morning will be a busy day at the Old State House: the crane will be onsite to lift the large support beams for the upper scaffolding.

Tuesday, March 25, 2008

Scaffolding Begins


This morning the staff at the Old State House came into work and saw partial scaffolding erected on the south side of the building. The first stage of scaffolding will reach the peak of the roof and will be finished prior to the coming weekend. The project began last night and more scaffolding will be added each night this week.